Dayton Mall-area traffic to deal with Ohio 741 project into fall

The Ohio Department of Transportation’s $3 million work is just north of Ohio 725, one of the busiest intersections in the Dayton area.

The work includes improved storm drainage, pedestrian access, sidewalk installation, traffic signal upgrades and asphalt resurfacing to Bauer Elementary School.

Traffic is being maintained throughout construction with occasional turn lane restrictions and lane closures through the corridor, according to the city.

RELATED: Miami Twp. may extend road, add traffic signal on Ohio 741

Traffic signal modifications along the corridor are underway, including a rebuild of the 725/741 signal with mast arms and additional overhead signage, according to Miamisburg City Engineer Bob Stanley.

Significant storm drainage, curb, gutter and sidewalk, and roadway work is complete on the east lanes of the corridor, he added.

Traffic maintenance has shifted and similar reconstruction work is underway on the west lanes of Ohio 741. Construction is expected to be complete by the end of the year, according to Stanley.

EARIER: Ohio to fund $1.9 million Miamisburg road reconstruction, widening

Thank you for reading the Dayton Daily News and for supporting local journalism. Subscribers: log in for access to your daily ePaper and premium newsletters.

Thank you for supporting in-depth local journalism with your subscription to the Dayton Daily News. Get more news when you want it with email newsletters just for subscribers. Sign up here.

X