The one exception was parts of the PJM region where capacity price increases were driven partly by data center demand, according to the study.
PJM is a massive regional transmission organization that manages the electric grid and wholesale electricity market across Ohio and several other states.
PJMâs benchmark capacity price increased by 833% between the 2024-2025 and 2025-2026 delivery years. Even after regulatory intervention that lowered price caps, PJMâs prices increased by an additional 22% for the 2026-2027 delivery year, which will affect future rates, according to the study.
A key factor in this increase was the surge in data center demand expected in the PJM region, which increased PJMâs projected capacity needs.
PJM state governors, including Ohio Gov. Mike DeWine, the U.S. secretary of energy and secretary of the interior signed a statement of principles in January to extend caps on the capacity prices that retail customers will pay, support the development of new generation capacity for data centers and ensure data centers pay for that capacity.
If implemented as proposed, the extended price cap would save more than 67 million consumers within the PJM region about $27 billion over the next two years.
DAYTON DAILY NEWS INVESTIGATES
The cost of data centers
Massive data centers are proposed to be built across southwest Ohio. Our investigation looks at the cost and consequences of these power-hungry, water-thirsty, tax-supported facilities.
Reporting by London Bishop and Bryn Dippold.
- » âLife-changing decisionâ: Data center growth fuels fears in local communities
- » Data centers driving up regional electric costs, study says
- » Impact of data centers on regional water supply âan emerging issueâ
- » Data centers get big tax breaks. Do they create jobs?
- » Ohio lawmakers show bipartisan support for data center legislation
- » Video: Passions run high as local town grapples with data center fears
The statement of principles aligns in many respects with PJMâs goals of managing the âsurge of large loads while balancing affordability and growing risk to grid reliability,â according to PJM External Communications Senior Manager Jeff Shields.
Capacity market auctions at PJM âprocure power supplies needed for grid reliability in future yearsâ and those wholesale power costs account for âonly a portion of the retail bill.â
âAcross PJM, electricity demand driven largely by data centers has outpaced the development of new power generation resources, resulting in a mismatch between demand and supply,â Shields said.
AES Ohio
The Charles River study noted that the largest retail rate impacts from PJMâs rate increases are felt by customers of utilities that do not generate their own power.
Electric rates can be broken down into three components: generation (producing electricity), transmission (moving it over long distances) and distribution (delivering it to homes and businesses), according to AES Ohio Corporate Communications Manager Mary Ann Kabel.
AES Ohio does not own generation, instead being a transmission and distribution provider regulated by the Federal Energy Regulatory Commission and Public Utilities Commission of Ohio.
All new customers, including large loads and data centers, apply for new service and provide details of electric requirements. AES Ohio then follows a âthorough processâ for evaluating data center requests, including initial inquires, site studies and service agreements.
âLarge load requests, including data centers, typically need transmission investments but also significantly increase usage,â Kabel said. âThat increased usage can offset those investments, reducing the transmission costs for other customers.â
Kabel said the company has an âobligation to serve customers who locate in our service territory.â
âWe ensure that the costs of any new transmission infrastructure upgrades are fairly reflected in our transmission rates,â she said.