The bridge was scheduled to reopen Friday, but was delayed due to bad weather.
The ailing bridge was closed in the fall of 2016 for a $6 million rebuild that features wider sidewalks, improved lighting and a new middle turn lane.
RELATED: Dayton replacing Helena Street bridge for $6M
Since 1999, the city of Dayton has invested almost $65 million to replace 11 bridges.
RELATED Dayton bridge project part of investment
When the Helena Street bridge reopens, work will begin on replacing the nearby Keowee Street bridge over the Great Miami River. The Keowee Street bridge, scheduled to close Jan. 2, is providing a detour route for the Helena Street bridge.
RELATED: Keowee Street detours delayed, but bridge will close for almost 2 years
Here’s a look at the completed Dayton bridge projects and their cost (in reverse chronological order):
Webster Street Bridge over the Mad River
Opened: November 2, 2017
Cost: $10.1 million
Broadway Street Bridge over Wolf Creek
Opened: September 16, 2013
Cost: $2.4 million
Rosedale Drive Bridge over Wolf Creek
Opened: October 25, 2011
Cost: $1.9 million
Philadelphia Drive Bridge over Wolf Creek
Opened: January 11, 2011
Cost: $3.4 million
Edwin C. Moses Boulevard Bridge over Wolf Creek (aka the Veterans Memorial Bridge)
Opened: May 13, 2010
Cost: $4.3 million
Stewart Street Bridge over the Great Miami River
Opened: November 30, 2009
Cost: $15.4 million
Dayton Expressway Bridge over Keowee Street
Opened: November 3, 2008
Cost: $6.6 million
Paul Lawrence Dunbar Street Bridge over Wolf Creek
Opened: July 29, 2008
Cost: $2.4 million
Washington Street Bridge over the Great Miami River
Opened: December 6, 2007
Cost: $7.6 million
Findlay Street Bridge over the Mad River
Opened: May 5, 2006
Cost: $4.5 million
Dayton bridge projects
Here’s a look at the completed Dayton bridge projects and their cost (in reverse chronological order):
Webster Street Bridge over the Mad River
Opened: November 2, 2017
Cost: $10.1 million
Broadway Street Bridge over Wolf Creek
Opened: September 16, 2013
Cost: $2.4 million
Rosedale Drive Bridge over Wolf Creek
Opened: October 25, 2011
Cost: $1.9 million
Philadelphia Drive Bridge over Wolf Creek
Opened: January 11, 2011
Cost: $3.4 million
Edwin C. Moses Boulevard Bridge over Wolf Creek (aka the Veterans Memorial Bridge)
Opened: May 13, 2010
Cost: $4.3 million
Stewart Street Bridge over the Great Miami River
Opened: November 30, 2009
Cost: $15.4 million
Dayton Expressway Bridge over Keowee Street
Opened: November 3, 2008
Cost: $6.6 million
Paul Lawrence Dunbar Street Bridge over Wolf Creek
Opened: July 29, 2008
Cost: $2.4 million
Washington Street Bridge over the Great Miami River
Opened: December 6, 2007
Cost: $7.6 million
Findlay Street Bridge over the Mad River
Opened: May 5, 2006
Cost: $4.5 million