ODOT nearly doubles grant to repair Xenia bridge

There will be construction on a bridge just south of downtown Xenia next summer.

Credit: Chuck Hamlin

Credit: Chuck Hamlin

There will be construction on a bridge just south of downtown Xenia next summer.

The Ohio Department of Transportation is nearly doubling a grant it is giving to Xenia to repair a bridge on South Columbus Street.

ODOT is increasing the grant amount from $340,000 to $659,000. Xenia’s share of the project will remain $18,000, said Xenia City Engineer Chris Berger.

The original grant from ODOT was based on a preliminary look at the project before the design had started. Once design of the bridge was finished, the city determined there were other parts of the bridge that needed to replaced that weren’t included in the preliminary plan.

The original estimated construction cost was to replace the existing bridge beams with a reinforced concrete box culvert under South Columbus Street, near the bike path crossing. The bridge goes over Shawnee Creek.

Construction is expected to begin on the bridge in the early summer of 2021 and last through the remainder of the year, Berger said. The bridge will be closed for up to three months.

Kathleen Fuller, ODOT spokeswoman for District 8, said traffic will likely be diverted to Detroit Street and Main Street.

This bridge replacement project is part of the Ohio Bridge Partnership Program, Fuller said. Most of the funds for this project are federal dollars, but are administered by ODOT, she said.

Xenia City Council approved a resolution on Dec. 10 allowing the city manager to enter into a local public agency (LPA) agreement, which will allow the city to undertake the bidding, awarding and administration of this program. Before this legislation, ODOT was going to responsible for this.

Construction started in September on the bridge on South Detroit Street over Shawnee Run and south of Leaman Street. The bridge work is on the base of the structure, removing sediment and adding material to protect the bridge, according to ODOT.

North of Xenia, construction crews will also be rehabilitating the bridge over Massie Creek, just south of state Route 235.

That project includes replacing the deck edges and other minor repairs. Major construction at this site won’t start until the spring of 2021, Fuller said.

About the Author